Beech Road  / Burrows Hill, Hartford.
CW&C Highways have summarised below the latest programme of works:-
 
1)    National Grid works – programmed to be complete by Saturday 29th October  2016.
2)    Junction improvement scheme – Installation of traffic Signals - Monday 31st October 2016 using 3 ways lights.
3)    Junction improvement scheme – Resurfacing of junction Wednesday 2nd November for 3 days under road closure (weather permitting)
4)    Junction improvement scheme – Commissioning of Traffic Signals – to follow on after resurfacing.  
 
Please note that the road closure between its junctions with Beech Road and Firdale Road has been programmed in the school holidays to keep disruption to a minimum. The contractor has been asked to keep the local residents informed about the programmed works. Information boards are to be erected on site to give warning of the road closure.
 
As you are aware, we have been working closely with National Grid to plan the project in conjunction with the Winnington Urban Village highway improvement works to keep the disruption to a minimum. There has been a lot of works in the Winnington and Northwich area recently and we are working hard to co-ordinate it as best as possible.
 
Andy Hamman
Principal Engineer
Cheshire West and Chester Council
 
Tel: 0300 123 7036
Email: This email address is being protected from spambots. You need JavaScript enabled to view it.
Location: Phoenix House, Clough Road, Winsford, CW7 4BD
Visit: cheshirewestandchester.gov.uk